For construction companies, a work-in-progress (WIP) schedule is more than a report on active jobs. It connects project-level information, including contract values, costs incurred, estimated costs to complete, billings, and expected gross profit, to the company’s financial statements. Because those inputs influence revenue recognition, contract assets and liabilities, working capital, and reported profitability, inaccurate or outdated information can affect far more than a single project.
The same information also helps management see how jobs are performing while there is still time to respond. Banks, sureties, outside accountants, prospective buyers, and other financial statement users may rely on it when evaluating the business. For that reason, WIP should be treated as both an accounting process and a management discipline, as a WIP schedule is only as reliable as the estimates and job-cost information behind it.
How WIP Reporting Connects to the Financial Statements
For many construction contracts that qualify for revenue recognition over time under Accounting Standards Codification Topic 606, revenue is recognized as the contractor satisfies its performance obligation. One commonly used approach is the cost-to-cost input method, which measures progress by comparing costs incurred to date with estimated total costs.
For example, assume a contractor has a $5 million contract and initially expects the project to cost $4 million. If the company has incurred $2 million of qualifying project costs and still expects total costs of $4 million, the project is approximately 50 percent complete using a cost-to-cost measure, which affects the amount of revenue and gross profit recognized to date.
If updated information shows that total expected costs are actually $4.5 million, the economics of the job have changed. Expected gross profit is lower, and the revised estimate needs to be reflected in the accounting. This is why estimated total cost, and estimated cost to complete, is one of the most important inputs on a WIP schedule.
Underbillings and Overbillings Affect the Balance Sheet
The WIP schedule also helps reconcile the relationship between revenue recognized and amounts billed to customers. Contractors often refer to these positions as underbillings and overbillings. Under current financial reporting terminology, they are generally reflected as contract assets or contract liabilities depending on the facts and circumstances.
A contract asset can arise when recognized revenue exceeds the amount the contractor has an unconditional right to bill, while a contract liability can arise when the contractor bills or receives consideration ahead of the related revenue recognition. These balances affect the balance sheet and can influence working capital and other financial measures used by lenders, sureties, and management.
Large or unusual changes in underbillings deserve attention, but is not automatically a problem. Management should understand what is driving the balance and whether it reflects normal contract terms and timing or something that requires action. Questions may include:
- Is the company behind on billing?
- Is there an unapproved change order?
- Are costs running ahead of the project plan?
- Is the estimated margin still realistic?
A useful WIP schedule should help management answer those questions and connect the billing position to what is happening on the project.
Gross Profit Fade Can Signal a Problem Earlier
One of the most useful trends to monitor is gross profit fade, which is a decline in a job’s estimated gross profit or gross margin as the project progresses. Some movement in expected profitability is normal as project conditions change, but repeated or significant deterioration can point to estimating problems, cost overruns, productivity issues, procurement challenges, poorly controlled change orders, or project management concerns.
For example, a job that began with an expected 20 percent gross margin and is now projected at 12 percent should prompt more than an accounting adjustment. Management should understand what changed and whether the same issue could affect other jobs. That analysis can improve decisions on the current project while also informing future estimating, bidding, and project management.
In that sense, profit fade is not simply a financial reporting outcome. It can be an early indicator of an operational issue that management can investigate before the project is complete.
Loss Jobs Require Prompt Attention
WIP analysis becomes especially important when a project is expected to lose money. Under U.S. GAAP, the loss guidance retained in ASC 605-35 for construction-type contracts requires the entire anticipated loss to be recognized when the loss becomes evident rather than spread over the remaining life of the project. (DART)
That requirement makes current, realistic cost-to-complete estimates essential. If project managers continue to carry an outdated estimate after field conditions, labor requirements, material costs, or other assumptions have changed, the financial statements may not reflect the full expected economics of the job. A regular WIP review gives management a structured opportunity to revisit those assumptions and confirm that projected costs still represent the best estimate based on what is known today.
What Contractors Should Review on Their WIP Schedules
An effective WIP review should go beyond confirming that the spreadsheet calculates correctly. Management should focus on the assumptions and information behind the calculations, with particular attention to the following areas.
Estimated Costs to Complete
Project managers should update projections regularly so estimates reflect current labor requirements, subcontractor commitments, material costs, known project difficulties, remaining scope, and other available information. Simply rolling forward last month’s estimate can conceal changes in job performance.
Contract Values and Change Orders
Contract values should be updated to reflect approved contract modifications, as appropriate. Unapproved or disputed change orders require particular attention because their accounting treatment depends on the underlying facts and circumstances, including whether enforceable rights and obligations exist and whether any additional consideration qualifies for recognition under the applicable revenue-recognition guidance.. Management should have a consistent process for identifying pending changes, evaluating their status, and determining how they should be reflected in financial reporting.
Gross Profit Trends
Estimated gross profit should be compared from period to period. Significant changes should be explainable, and recurring profit fade should direct management’s attention to jobs that may require a deeper operational review.
Billing Positions
Significant underbillings and overbillings should be reviewed in depth rather than accepted at face value. A billing position may be reasonable based on contract terms and project timing, or it may point to issues involving billing practices, job performance, change orders, or cash flow.
Job Cost Coding
Costs need to be recorded to the correct jobs and cost categories. A miscoded cost can distort a project report, and when a company uses a cost-to-cost measure of progress, it can also affect revenue recognition and reported profitability.
Retainage
Retainage should be clearly identified and reconciled. Management should understand the amount outstanding, the projects involved, and the expected timing of collection or payment because retainage can affect receivables, payables, and cash-flow expectations.
Loss Contracts
Projects expected to finish at a loss should be identified promptly so the accounting reflects the applicable loss-recognition requirements. Delaying that assessment until project completion can result in a significant adjustment later.
Reconciliation to the General Ledger
The WIP schedule should reconcile with the accounting records. When project reports, billing records, job-cost systems, and the general ledger operate independently, unexplained differences can accumulate. Those differences should be investigated and resolved rather than carried from one reporting period to the next.
How WIP Consulting Can Strengthen the Process
Even companies with experienced accounting teams and project managers can benefit from an outside review of the WIP process, particularly when the same team has worked with the same jobs and reports for an extended period. An independent perspective can help identify inconsistent assumptions, reporting gaps, or questions that may no longer be obvious internally.
At HBK, our WIP consulting approach examines both the numbers and the process used to develop them. Depending on the contractor’s needs, that can include reviewing cost-to-complete estimates, job-cost reporting, billing positions, margin trends, change orders, loss jobs, and the reconciliation between operational reporting and the financial statements.
An outside review can also help management establish a more consistent WIP meeting process and define the questions project managers should be prepared to answer each reporting period. The goal is to create WIP information management can rely on to understand project performance, anticipate financial-statement effects, and make better-informed operating decisions. The strongest process connects accounting, estimating, project management, and financial reporting rather than treating them as separate functions.
Better WIP Information Supports Better Business Decisions
Reliable WIP reporting has value beyond month-end or year-end financial statements. Management can use it to evaluate which types of projects are generating expected returns, identify recurring estimating issues, anticipate cash-flow needs, assess backlog quality, and make more informed decisions about future bidding and staffing.
The same information becomes increasingly important when outside stakeholders are involved. Sureties evaluate a contractor’s financial capacity as part of the underwriting process and request financial and operational information to evaluate capital and capacity. (Surety) Banks and other lenders may focus on working capital, leverage, profitability, and cash flow, while buyers and advisors involved in an ownership transition or transaction may examine historical job performance and the reliability of management’s estimates.
In each case, the quality of the WIP process supports the credibility of the financial information being presented and gives management a stronger basis for explaining what is happening across the business.
For companies with active construction projects, WIP is generally most useful when reviewed consistently throughout the year rather than prepared only for year-end financial reporting. The appropriate frequency depends on project size, duration, and complexity, but estimates should be updated often enough to identify meaningful changes promptly.
No single number tells the entire story, but estimated total cost, and therefore estimated cost to complete, is one of the most important inputs. If that estimate is inaccurate, the calculated percentage of completion, expected gross profit, and related financial reporting can also be affected.
No. A large underbilling can arise for legitimate reasons, including contract billing provisions or project timing. Management should still understand significant balances and determine whether they relate to billing delays, change orders, project performance, or other issues.
Gross profit fade occurs when a project’s expected gross profit declines as the job progresses. It can result from cost overruns, productivity issues, estimating changes, scope changes, or other project conditions and should be investigated when it becomes significant or recurring.
Yes. WIP consulting can complement year-end tax, review, or audit services by helping management improve the internal process used to develop job estimates and financial information throughout the year. The focus is on improving the reliability and usefulness of the information before year-end reporting begins.
Make WIP a Management Tool, Not Just a Year-End Schedule
For construction companies, WIP reporting sits at the intersection of operations and accounting. A strong process gives management a clearer view of profitability while jobs are still underway, supports more reliable financial reporting, and creates better information for conversations with banks, sureties, accountants, owners, and other stakeholders.
If the WIP schedule is primarily updated for the outside CPA at year-end, or if management has concerns about job margins, billing positions, estimated costs to complete, or differences between job reports and the general ledger, a more detailed review may be appropriate. HBK works with construction companies to evaluate WIP schedules and the processes behind them, identify areas that warrant attention, and improve the usefulness of WIP reporting as a financial and operational management tool.